SWARMP and Unsafe Repairs: Timelines and What to Do

AM
About the Author

Andrew Mitchell

Andrew Mitchell works in building restoration at Local Law 11 Brooklyn. He covers facade repair planning, masonry restoration and construction requirements associated with FISP findings. His articles help property owners understand repair scopes, documentation and the process of addressing reported facade defects.

When I review facade inspection findings with building owners, I pay close attention to the rating assigned to each condition. That classification affects how urgently you need to act, what protection may be required and how you should plan the work.

Under New York City's Facade Inspection and Safety Program (FISP), a report generally classifies a building's exterior wall conditions as Safe, Safe With a Repair and Maintenance Program (SWARMP), or Unsafe. These ratings are not interchangeable. Understanding the difference helps you prioritise the right work instead of treating every defect as an ordinary maintenance item.

An Unsafe finding requires prompt public protection and correction within the applicable DOB timeframe, generally 90 days from the initial report filing. SWARMP means a condition is considered safe at the time of inspection but needs attention within the period specified in the report. If the condition remains uncorrected and is reported again at the next inspection, it is classified as Unsafe under the program's rules.

The Three Ratings

I recommend starting with the actual inspection report. It identifies the observed conditions, their classifications and the actions required for the particular building.

Safe
No reportable defect requiring this type of corrective action was identified at the time of inspection.
Continue routine maintenance and monitor the facade.
SWARMP
The condition is considered safe at present but requires attention within the period specified by the report.
Plan the work, obtain estimates and complete it within the applicable timeframe.
Unsafe
A condition presents a hazard that requires immediate attention and appropriate protection.
Arrange public protection promptly, correct the condition and meet DOB filing requirements.
Sidewalk shed and scaffolding on a Brooklyn facade during inspection

What to Do If Your Facade Is Unsafe

When an inspection identifies an immediate facade hazard, I would not wait for a routine board meeting or the next budget cycle before arranging the necessary protection. Contact your QEWI and appropriate contractors to establish the required actions.

  1. Install Protection Immediately The priority is protecting pedestrians and other people who could be exposed to the hazard. Depending on the condition and site, measures may include a sidewalk shed, fencing, netting or another approved protective arrangement. The required setup depends on the location and nature of the hazard. Applicable permits and safety requirements must be confirmed before installation. A sidewalk shed may also require coordination around entrances, pedestrian routes, deliveries and neighbouring properties.
  2. Repair Within 90 Days DOB generally requires identified Unsafe conditions to be corrected within 90 days of the initial report filing. The precise obligations and dates should be confirmed with your QEWI and the official filing record. I recommend obtaining a written scope of work as early as possible. It should identify the affected areas, proposed construction methods, access requirements and any approvals that may be needed. This helps the owner compare estimates without losing sight of the required completion date.
  3. Amended Report Once all reported hazardous conditions have been corrected, the QEWI must complete the required follow-up filing. DOB's applicable procedure generally requires an amended report within two weeks after correction of all Unsafe conditions. Keep records of the completed work, including photographs, invoices and relevant contractor documentation. These records can help the QEWI verify the work and prepare the necessary submission. Confirm the exact filing deadline with the inspector and DOB.
  4. Extension If Needed Some projects take longer than expected because of concealed damage, access limitations, material availability or approval requirements. If the required work and amended filing cannot be completed within 104 days of the initial report filing, an extension request may be necessary. I always tell owners to raise scheduling problems as soon as they become apparent. Ask your QEWI which extension process applies, what documentation is needed and when the request must be submitted. Do not assume an extension is automatic or that making a request removes existing safety obligations.

What to Do If Your Facade Is SWARMP

Practical Steps

A SWARMP finding allows the owner to organise work before the condition becomes hazardous. Here are the steps you can take:

  • Confirm the projected date. Ask your QEWI to identify when the condition may become hazardous and clarify the applicable completion timeframe.
  • Get estimates early. Give qualified contractors the relevant report sections, photographs and access information so they can assess the scope.
  • Prioritise significant defects. Corroded lintels, deteriorating parapets and loose masonry may need early attention based on the inspector's findings.
  • Keep a record. Save photographs, proposals, invoices, permits where applicable and completion records for the building's maintenance file.
  • Coordinate with management. For co-ops and condos, establish who approves the budget, informs residents and arranges access.

For steel lintels showing corrosion or related masonry damage, review our lintel repair and replacement service. The appropriate method depends on the observed condition and the professional assessment.

Brooklyn pre-war masonry apartment buildings with facade detailing

Why SWARMP Shouldn't Wait

A condition labelled SWARMP is not a permanent permission to postpone work. It means the defect is considered safe at the time of inspection, with action required within the specified period.

If a previously reported condition remains uncorrected and is reported again at the next inspection, it is classified as Unsafe under the program's rules. That can trigger urgent protection measures, a compressed construction schedule and additional costs.

I encourage owners to use the report as a planning document, not something to file away until the next inspection cycle. Addressing defects in a planned manner can make budgeting and coordination more manageable.

Brooklyn Examples

Different building types can present different facade concerns. In older masonry properties in Park Slope, Crown Heights or Brooklyn Heights, common findings may include mortar loss, cracked masonry, deteriorated parapets and corrosion around embedded steel.

On waterfront towers in Williamsburg, balconies and exposed facade elements may face different combinations of weather exposure, water infiltration and material deterioration. Landmark status may add time where proposed exterior changes require review by the NYC Landmarks Preservation Commission.

Waterfront residential tower facade with balconies and exposed metal

Frequently Asked Questions

What does SWARMP stand for?

SWARMP stands for Safe With a Repair and Maintenance Program. It describes a facade condition considered safe at the time of inspection but requiring corrective work within the period specified in the report. Owners should review the projected hazard date and plan accordingly.

How long do I have to fix an Unsafe condition?

DOB generally requires correction within 90 days of the initial report filing. If the work and required amended report cannot be completed within 104 days of that filing, an extension request may be needed. Confirm the applicable dates and procedures with your QEWI and DOB.

Do I need a shed for SWARMP?

Not necessarily. A SWARMP classification does not automatically mean a sidewalk shed is required. The protection needed depends on the actual site conditions and applicable safety requirements. Ask your QEWI to clarify whether any immediate protective measures are necessary.

Can an Unsafe rating change to Safe?

A corrected condition can be reflected in the required amended filing after the QEWI verifies the work and submits the appropriate documentation. The final status depends on the completed work, the professional's findings and DOB's records. Do not assume the status changes automatically when construction ends.

Who decides the rating?

The QEWI determines the facade condition classification and documents it in the technical report. A contractor may recommend construction methods and perform the agreed work, but does not replace the QEWI's professional inspection and reporting responsibilities.

Is DOB's repair window the same everywhere in the report?

No. The required actions and dates depend on the classification, report details and applicable DOB procedures. Review each finding with your QEWI and confirm filing dates in DOB NOW. If different records appear inconsistent, seek clarification before relying on a deadline.

Need Help Planning Facade Work?

I recommend acting as soon as an inspection identifies a defect that needs attention. Early planning gives owners more time to understand the scope, coordinate access, obtain estimates and arrange the required documentation.

Our team can discuss construction needs involving masonry, lintels and facade access. Share your inspection findings and building address through the contact page so we can discuss the next steps for your project.

Have a SWARMP or Unsafe finding?

Share your inspection findings and building address. Our team can discuss the construction scope, access requirements and documentation needed for your project.

Ready to discuss your project?

Contact Us

Disclaimer: Regulatory information reviewed October 2026. DOB requirements and procedures may change. Confirm latest obligations and deadlines with NYC DOB and your QEWI before acting.